OSBC | Osun State Broadcasting Corporation
  • Home
  • About
    • Our History
    • Management Board
    • Management Team
    • Other Management Staff
    • OSBC Organogram
  • Contact
  • LIVE TV/RADIO
    • 104.5FM RADIO LIVE
    • OSBC TV LIVE
    • REALITY 96.3FM RADIO LIVE
    • ORISUN 89.5FM LIVE
    • 104.5FM Radio Live Video
    • Orisun FM Live Video
    • REALITY Radio Live Video
  • PODCAST
    • Saturday Morning Treat – SMT
    • Dateline
    • Newsmaker
    • In the Newsroom
    • Kajoso
    • Ojumo’re
    • Newspaper Today
  • Portal
    • Staff Email
  • Osun state Website
No Result
View All Result
  • Home
  • About
    • Our History
    • Management Board
    • Management Team
    • Other Management Staff
    • OSBC Organogram
  • Contact
  • LIVE TV/RADIO
    • 104.5FM RADIO LIVE
    • OSBC TV LIVE
    • REALITY 96.3FM RADIO LIVE
    • ORISUN 89.5FM LIVE
    • 104.5FM Radio Live Video
    • Orisun FM Live Video
    • REALITY Radio Live Video
  • PODCAST
    • Saturday Morning Treat – SMT
    • Dateline
    • Newsmaker
    • In the Newsroom
    • Kajoso
    • Ojumo’re
    • Newspaper Today
  • Portal
    • Staff Email
  • Osun state Website
No Result
View All Result
OSBC | Osun State Broadcasting Corporation

Mass Metering: FG To Distribute Four Million Units – FG

OSBC_Admin by OSBC_Admin
January 18, 2023
in electricity
0
0
SHARES
1
VIEWS
Share on FacebookShare on Twitter

The Federal Government says four million metres will be distributed in the second phase of the ongoing National Mass Metering Programme.

Special Adviser to the President on Infrastructure, Ahmad Zakari, who made a live appearance on Channels Television’s Sunrise Daily on Wednesday, added that one million units were deployed in the first phase of the programme.

“President [Muhammadu] Buhari actually withheld some funding that was available from the World Bank for a short period of time to allow us to restructure the Discos and we have a World Bank facility that will fund another 1.25 million metres.

“So, what I would say is we know the gap when we started was about 9.8 million metres. One million has been done by the first phase of the National Mass Metering Programme.

“Another four million will be done by the second phase, which should commence shortly. Then another one million – funding has been secured and procurement will commence [later],” he said.

Asked when the second phase would begin, he said, “It should start this first quarter… before March.”

Zakari alluded to the Nigerian Electricity Management Services Agency (NEMSA) overseeing more than 20 new local manufacturing companies onboarded to assemble the procured metres.

Previous Post

Emefiele To Meet With Governors Over New Policy

Next Post

Election: IMS Trains Women Journalists On Efficiency, Capacity Building

Next Post

Election: IMS Trains Women Journalists On Efficiency, Capacity Building

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

OSBC | Osun State Broadcasting Corporation

© 2023 OSBC - Osun State Broadcasting Corporation | Designed by: ICT UNIT.

Navigate Site

  • Home
  • About
  • Contact
  • LIVE TV/RADIO
  • PODCAST
  • Portal
  • Osun state Website

Follow Us

No Result
View All Result
  • Home
  • About
    • Our History
    • Management Board
    • Management Team
    • Other Management Staff
    • OSBC Organogram
  • Contact
  • LIVE TV/RADIO
    • 104.5FM RADIO LIVE
    • OSBC TV LIVE
    • REALITY 96.3FM RADIO LIVE
    • ORISUN 89.5FM LIVE
    • 104.5FM Radio Live Video
    • Orisun FM Live Video
    • REALITY Radio Live Video
  • PODCAST
    • Saturday Morning Treat – SMT
    • Dateline
    • Newsmaker
    • In the Newsroom
    • Kajoso
    • Ojumo’re
    • Newspaper Today
  • Portal
    • Staff Email
  • Osun state Website

© 2023 OSBC - Osun State Broadcasting Corporation | Designed by: ICT UNIT.

Enable Notifications OK No thanks